MMWEC – Breathe Clean North Shore https://breathecleannorthshore.org Wed, 28 Aug 2024 20:56:16 +0000 en-US hourly 1 https://wordpress.org/?v=6.7 https://i0.wp.com/breathecleannorthshore.org/wp-content/uploads/2021/05/B.png?fit=14%2C32&ssl=1 MMWEC – Breathe Clean North Shore https://breathecleannorthshore.org 32 32 193038625 Peakers on Pulaski Street in Peabody https://breathecleannorthshore.org/2024/08/28/peakers-on-pulaski-street-in-peabody/ Wed, 28 Aug 2024 20:40:22 +0000 https://breathecleannorthshore.org/?p=2948   It’s been nearly a decade since SP2015A entered our purview.  While in the early days there wasn’t much information, we now have a boatload of info about MMWEC’s new peaker and, for the first time, cumulative statistics that include PMLP’s two gas-and-oil burning generators located next door.
    The Waters River Power Station has grown to include the city’s two old generators and the new peaker owned by Mass. Municipal Wholesale Electric Company (MMWEC) on the same city owned lot. The state views this arrangement as two separate owners and therefore the project did not have to meet some requirements (i.e., full environmental and health review) because, individually, the owners’ generators create less than 100MW of power.  Cumulatively, the site creates 128MW of power. 
      PMLP, with approximately 26,000 customers, is the third largest of 40 municipal electric utilities in the state. Its power supply comes from a variety of sources throughout the Northeast, including : two generators in Peabody owned and operated by PMLP as well as three exhaust emission stacks, three aboveground fuel oil storage tanks (110,000 gallon capacity each), and a 115 kilovolt (KV) substation whose interface with the transmission system is controlled by REMVEC, a satellite of the Independent System Operator-New England (ISO-NE).
      Last month, the PMLP Commission approved $2.5 million dollars to upgrade their 115 kilovolt substation equipment at Waters River and Bartholomew Street substations.  PMLP Manager Joe Anastasi said the required improvements at the 48-year-old, high-voltage substation were needed before the MMWEC project was added to the site.  The arrangement means the city pays for it and MMWEC rents space.  The amount of “rent” was not provided but to get  MMWEC’s generation through Peabody’s  substation and out the door to the transmission system, it goes through some of this new equipment.
      In 2023, while MMWEC’s new peaker was being built, a  20-gallon, #2 diesel oil spill resulted from work on the new peaker plant. Thirty cubic yards of contaminated soil was removed from the Pulaski Street site.  The release affected crushed stone and two catch basins that daylight into a nearby stream.  A boom was placed into the catch basins. Not sure which entity paid for the clean-up or if the cost was shared.

]]>
2948
Officials won’t say how often new peaker runs https://breathecleannorthshore.org/2024/08/28/officials-wont-say-how-often-new-peaker-runs/ Wed, 28 Aug 2024 20:25:22 +0000 https://breathecleannorthshore.org/?p=2942  Salem News, Caroline Enos, Aug. 15, 2024, Page 1

PEABODY — A controversial 60 megawatt peaker plant is now online on Pulaski Street. But developers behind the $85 million plant won’t share how often it’s running — or if it’s running at all.
      The natural gas and oil-powered plant is operated by the Massachusetts Municipal Wholesale Energy Company and sits on a Peabody Municipal Light Plant site at 58R Pulaski St. The site is owned by the city of Peabody.
    It’s meant to operate only during “peak” energy use times. Typically, to prevent the power grid from becoming overstressed on especially hot or cold days.
    The plant is expected to run for 239 hours annually, well below the cap of 1,250 hours per year as regulated by the Massachusetts Department of Environmental Protection, according to PMLP’s website. It supplies capacity to 14 municipalities across the state who signed on to the project, including Peabody, Marblehead and Wakefield locally.
    The peaker went online June 1.
    When asked by The Salem News how often the peaker has run since then, or if it has operated at all, developers behind the project said they cannot say. Doing so violates rules designed to protect “competitively sensitive information” by grid operator ISO New England, MMWEC spokesperson Kate Roy said.
    “It is not that MMWEC ‘won’t release the data,’ it is that MMWEC can’t release the data,” she wrote in an email. “The electricity market is competitive and … the (peaker) can be called upon by the ISO when needed.
    “If suppliers of electricity to the competitive market knew what units were supplying power when, then there is the clear danger of market price manipulation,” Roy continued. “So the ISO requires the confidentiality of this information.”
      ISO does release aggregated data on the types of fuel used to power New England’s grid each day and how many megawatt hours of energy they produce. Just nothing on individual generators.
    “This policy is designed to maintain a fair and competitive energy market by protecting generator-specific data to prevent unfair advantages and by ensuring electricity prices are driven by supply and demand — not strategic exploitation,” ISO spokesperson Mary Cate Colapietro said.
    The Peabody Lighting Commission itself is not privy to when the peaker runs as it is an MMWEC owned and operated project, Commission Chair Raymond Melvin said.
    “It might have started once or twice, but I don’t believe it’s fully operational,” he told The Salem News Wednesday. “When it does run, I’ll issue a press release.”
      Peabody resident Susan “Sudi” Smoller, founder of Breathe Clean North Shore and one of the loudest voices against the project, said the ISO’s rule “is a convenient way to not tell people what’s going on.
      “Do I have to organize a viewing party to see when the smokestack is running? At this point, yes,” she said.
      Smoller already hosted a handful of protests against the plant in 2021 and 2022, around the time construction started on the project, with other environmental groups in the state and was featured in the documentary “#StopPeabodyPeaker,” released over the winter.
    Facilities such as the Peabody peaker are typically required to submit annual CO2 emission reports to the DEP each January, a MassDEP spokesperson said.
      Peabody Health Director Sharon Cameron asked MMWEC this spring if the city’s Board of Health will receive air quality testing results from the peaker, along with notice of when the plant will run.
      Revealing when the plant operates violates “trade secrets,” Cameron was told, and emission data would later become available through MassDEP and also Form EIA-923 reports on the U.S. Energy Information Administration’s website.
      MMWEC is required to report operation data through this form annually for its plants that provide capacity to the grid and can produce at least 1 megawatt of power, according to the EIA. These plants can also be selected to submit this data for less comprehensive, monthly versions of this report released throughout the year, as was the case for MMWEC’s Stony Brook Plant in June.
      Purple Air monitors operated by the city track air quality data around Peabody. However, the one on Pulaski Street near the peaker hasn’t been working properly and Cameron had to apply for a new device from MassDEP in May. She has yet to hear back on the request, she said.
    As of now, there’s no public source for real-time data about Peabody’s new peaker.
    “You’d think (plant developers) would be eager for people to know how well it’s going, right?” state Rep. Sally Kerans said.
    Kerans, the Peabody Board of Health, state Sen. Joan Lovely and Wakefield Town Councilor Julie Smith-Galvin have been critical of a fossil fuel plant being built in an environmental justice area with higher rates of health disparities among residents and without any environmental or health impact studies done before the construction of the plant.
    The project wasn’t required to conduct the studies during its approval process, though it would have to if it sought approval today under the state’s Climate Policy Roadmap passed in 2021.
    The peaker is more energy efficient than the two existing generators at PMLP’s Pulaski Street substation. The oldest, built in the 1970s, will be delisted by June 1, 2026, PMLP General Manager Joe Anastasi said.
      The peaker is also capable of burning hydrogen, a green energy source. But the original equipment manufacturer is still testing the use of hydrogen in similar units and it is unclear when or how much hydrogen will be used in the peaker, Roy said.
    “MMWEC has supported efforts at the federal level to develop green hydrogen sources in the region,” she said. “Unfortunately, the federal government has not selected the region for a green hydrogen hub.”
      Nearly a decade on, the approval process of the plant itself remains a sore spot for opponents.
    Originally named Project 2015A for the year it went into development, discussions about the peaker started locally in executive sessions of the Peabody Lighting Commission in June 2015.
    The peaker’s name was changed to the Northeast Reliability Center earlier this year.
    The commission voted unanimously in late 2015 during one of these executive sessions for Peabody to participate in the project’s early development stages. The project was brought before the public by the commission for the first time at a regular meeting in October 2016.
    This was to keep the bidding process and other aspects of the deal that could be considered trade secrets confidential, Commissioner William Aylward, who was on the commission at the time of the vote, told The Salem News last year after the minutes of these 2015-2016 executive sessions were released.
    “(MMWEC) was still in the process of getting bids on who was going to do the build and who was going to do the equipment, where they were buying all this stuff from,” he said at the time. “That’s why some of these things have to happen in executive session.”
    Outcry against the project began in late 2020, when the state issued an air quality permit for 2015A. While the project had been discussed in general Lighting Commission meetings prior, residents hadn’t been adequately notified of the project, Ward 3 Councilor Stephanie Peach said.
    Peach represents the neighborhood where the peaker is situated and lives nearby. She told The Salem News she didn’t know until a reporter’s phone call this week that the peaker had been operational as of June 1.
    “We should be able to know when it’s running, not just as neighbors to the plant but as consumers in general,” Peach said.
      “People who pay PMLP for these services, it’s good for us to know when we’re peaking so that we know to conserve energy.”

]]>
2942
New Peabody ‘peaker’ power plant prepares to go online less green than promised https://breathecleannorthshore.org/2024/07/06/new-peabody-peaker-power-plant-prepares-to-go-online-less-green-than-promised/ Sat, 06 Jul 2024 19:16:25 +0000 https://breathecleannorthshore.org/?p=2929 BCNS was interviewed by Sophie Hartley and Hannah Richter, graduate students at MIT, last Fall.. This story is a collaboration between GBH News and an investigative journalism class at MIT’s Graduate Program in Science

WGBH July 05, 2024

The new Peabody power plant will soon start up for the first time, but it won’t be running on clean fuel as officials once assured. It will burn diesel and natural gas.

The Massachusetts Municipal Wholesale Electric Company initially proposed using fossil fuels for the so-called “peaker plant.” The nonprofit utility said in its 2016 proposal that the $85 million project would only operate at peak times of energy demand, typically the coldest and warmest days of the year, when the energy grid is otherwise overdrawn. The goal was to keep the power on without having to raise energy prices on those high-demand days.

But after activists and healthcare providers raised concerns about increased air pollution and carbon emissions, MMWEC changed course. In 2021, the utility announced it would operate the plant with a blend of green hydrogen and natural gas fuel, and eventually shift fully to hydrogen.

That plan now seems to be on hold. Joe Anastasi, manager of the Peabody Municipal Light Plant, said the plant is equipped to burn natural gas, oil and hydrogen — but, in part due to supply chain issues, the utility has not been able to procure any green hydrogen to burn.

And the plant is near opening. Spokeswoman Kate Roy said in an email that it is waiting to be dispatched by the regional electric grid, which she said could happen “any day now.”

The news has disappointed climate activists.

“[Peabody] could have been the first in the state to say no to burning more fossil fuels,” said Sudi Smoller, the founder of Peabody environmental advocacy group Breathe Clean North Shore. “We would have found a way. That’s what people do.”

Apart from a brief notice MMWEC published in the local paper in 2016, the peaker went largely unnoticed by the public for five years.

Then, in March 2021, the local Sierra Club urged members to oppose the natural gas and diesel plant. Activists questioned the timing: By 2050, Massachusetts’ electric grid must reach net zero carbon emissions, according to a 2021 state law. They wondered why the utility would put a new fossil fuel plant on the grid when cleaner alternatives were available.

That May, 87 Massachusetts healthcare professionals signed a letter calling for “an end to this misguided project,” citing air quality concerns and health inequities. The plant would emit 51,000 tons of carbon dioxide per year, the letter said, which would be equivalent to adding 11,000 cars on Massachusetts roads.

“The residents of Peabody currently have higher than state average rates of air-pollution related illnesses, and the air pollution associated with the new plant will increase mortality within the Peabody community,” the letter said.

State officials, climate activists and Peabody residents also spoke out against the plant, voicing anger about its proximity to a daycare and small businesses. 

In response, MMWEC announced a 30-day “pause” to address the concerns. MMWEC noted it was “an unusual step” for a project permitted years earlier, but they acknowledged technology had advanced since 2016. “Can we find a way to develop a needed capacity resource that isn’t fossil fuel-fired but still reliable in times of need?” said Ron DeCurzio, MMWEC’s chief executive, in the statement.

In June 2021, MMWEC announced a new plan. In a public meeting, Ed Krasinski, a project consultant, said the goal was to open the plant the following year with a blend of 75% natural gas and 25% green hydrogen. He said that Mitsubishi, the company that manufactured the plant’s turbine, was “aggressively pursuing” this target.

Krasinski also said that Mitsubishi hoped to increase its turbine’s capacity to a blend of 80% hydrogen by 2030.

“With regards to the project, we’re looking at converting to 100% green hydrogen post-construction,” said Brian Quinn, MMWEC’s director of engineering and generation assets. “The whole goal is to have green hydrogen refuel our future, and we’re on the way to doing that.”

On paper, MMWEC proposed a more measured shift. In a November 2021 bond offering, MMWEC stated the plant would begin operating with a 10% hydrogen blend, and achieve up to a 20% hydrogen blend by 2030, rather than the 80% suggested at the meeting. Depending on “advancements in technology,” the document said, “the green hydrogen mix may increase before and after 2030.”

Anastasi said MMWEC told him recently that the plant is equipped to accommodate a maximum 30% hydrogen fuel blend. 

When asked about the differences in projections, Roy said that because the technology and process was new, “expectations can change throughout the research and testing process.” 

Roy said that Mitsubishi was still testing the use of green hydrogen, so “we’re not exactly sure what percentage of green hydrogen will be incorporated and when.” She said MMWEC is committed to using green hydrogen “when it is feasible to do so.”

MMWEC recently updated its website to remove previous posts about the peaker plant and created a new page calling the plant the Northeast Reliability Center. The site says it will be online in 2024, and will be “fueled by natural gas, with oil as a backup, retro-fitted for green hydrogen.”

https://www.wgbh.org/news/local/2024-07-05/new-peabody-peaker-power-plant-prepares-to-go-online-less-green-than-promised?fbclid=IwZXh0bgNhZW0CMTEAAR0XUmC5yitPYWVr9Kvr3rXoJi9cbMMi2OANUW5nmLwjKsXQtGCYnCuUTbA_aem_G3yz7nRMSUDn6NzywoYLSw

]]>
2929
Peabody is part of this ‘First-in-kind’ Massachusetts program to introduce grid-scale battery storage https://breathecleannorthshore.org/2024/05/04/peabody-is-part-of-this-first-in-kind-massachusetts-program-to-introduce-grid-scale-battery-storage/ Sat, 04 May 2024 17:18:13 +0000 https://breathecleannorthshore.org/?p=2891 from Renewable Energy World

‘First-in-kind’ Massachusetts program to introduce grid-scale battery storage

Lightshift Energy and MMWEC deploy “first-of-its-kind” program for grid-scale battery energy storage in Massachusetts. (Pictured: Lightshift Energy project in Danville, VA) (Photo: Business Wire)

The Massachusetts Municipal Wholesale Electric Company (MMWEC), the Commonwealth’s designated joint action agency for municipal utilities, and Lightshift Energy, an energy storage project developer, owner, and operator, announced a “first-in-kind” program for the industry to deploy the state’s first jointly implemented fleet of grid-scale battery energy storage systems (BESS).

Lightshift will build up to 50 MW of BESS across MMWEC’s growing utility membership, which represents half of all the municipal utilities in the state, serving nearly 200,000 customers. Lightshift said the partnership could provide over $200 million in cost savings for municipal customers while enabling effective management of generation and load to help the Commonwealth reach its goals of net zero emissions by 2050.


GO DEEPER: Check out the Factor This! energy storage podcast playlist, including episodes on battery storage, long-duration energy storage, gravity storage, and more. Subscribe wherever you get your podcasts.


As part of the agreement, participating utilities within MMWEC’s membership will host one or more Lightshift energy storage projects. The initial wave of projects will commence operations this summer, with four projects already under construction in the towns of Groton, Holden, and Paxton. Late-stage development activities are already underway in the towns of Peabody, Shrewsbury, Wakefield, Chicopee, Ipswich, and Princeton, with mid-stage development activities moving forward in several other communities. Groton and Wakefield projects, among others, will provide backup power to critical infrastructure. The growing portfolio is scheduled to come online throughout 2024 and 2025.

“MMWEC is pleased to partner with Lightshift Energy on this battery energy storage system project,” says MMWEC Chief Executive Officer Ronald C. DeCurzio. “The project demonstrates yet again how the municipal utilities are leading the way in decarbonization in Massachusetts, in alignment with the Commonwealth’s emissions reduction targets.”

Cost-savings will be driven by “peak shaving” activities. Lightshift’s systems will be charged during periods of lower energy consumption and discharged during times of peak energy demand.

“This is a significant milestone for Massachusetts and for the participating utilities which are demonstrating leadership in grid modernization while prioritizing cost reduction for their communities,” said Rory Jones, Lightshift Co-Founder and Managing Partner. “And MMWEC has been pivotal in facilitating this first-in-kind program that other states will look to as a means to achieve major impact through community-based storage, at scale. Our partners in Groton, Holden, and Paxton have demonstrated particular leadership in bringing this program to life.”

Share

    

Lightshift will build up to 50 MW of BESS across MMWEC’s utility membership, which represents half of all municipal utilities in the state.

https://www.renewableenergyworld.com/…/first-in…/…

]]>
2891
A Peabody Peaker Battery https://breathecleannorthshore.org/2023/11/10/a-peabody-peaker-battery/ https://breathecleannorthshore.org/2023/11/10/a-peabody-peaker-battery/#respond Fri, 10 Nov 2023 20:09:10 +0000 https://breathecleannorthshore.org/?p=2792 Peabody and MMWEC (Ma. Municipal Wholesale Electric Co.) have come a long way to embrace renewable battery storage. During meetings in 2020 about SP2015A, the third gas-and-oil burning generator off Pulaski Street, battery storage was nixed as an alternative to. building new $85 million fossil fuel infrastructure.

Both MMWEC and PMLP officials stated during public meetings that batteries are not a feasible replacement for the proposed plant because batteries are expensive, require more space than is available and would fail to provide adequate reliability to the electric grid.

“MMWEC said that batteries would not work for Peabody because there was not enough room on the site,” said Jane Dye of CHEF, Citizens for Holden’s Energy Future. “Our response was “What? Batteries don’t have to all be in the same place. Spread them around to different MLPs (muncipial light plants).”

That’s what’s happening. Fourteen MMWEC communities, including Peabody, have partnered wiith MMWEC and Delorean Power LLC (Delorean), a Virginia-based, energy storage project developer, owner and operator. The first 5MW battery energy storage facility is planned in Holden Mass.

PMLP’s website includes information about a utility battery storage facility. “Battery Storage reduces our bulk power costs by allowing us to store power when it is cheaper for us to buy (during non-peak times), and then to use the battery to shave the peak which helps to reduce stress on the bulk power system and reduces PMLP’s transmission and capacity costs. This will be a collaborative project with MMWEC, and is targeted to be installed on PMLP’s property at 201 Warren Street Ext.” https://pmlp.com/224/Current-Projects

The resulting shift in energy demand from on-peak to off-peak hours will lead to significant cost and environmental benefits for customers in the 14 communities involved. But, Peabody’s customers will also see a reduction in air pollution since our three oil-and-gas burning peaker plants should run less.

The energy storage project is the first in a series that Delorean has developed with facilitation from MMWEC. In late 2022, Delorean won an exclusive partnership to build similar energy storage projects across the state with many expected to finish construction by the end of 2024.

https://www.salemnews.com/…/article_7e98ab0c-d97c-5ea0…

]]>
https://breathecleannorthshore.org/2023/11/10/a-peabody-peaker-battery/feed/ 0 2792
A peek at the new peaker on Pulaski https://breathecleannorthshore.org/2023/10/28/a-peek-at-the-new-peaker-on-pulaski/ Sat, 28 Oct 2023 15:04:33 +0000 https://breathecleannorthshore.org/?p=2776 A glimpse of the new $85 million gas-and-oil burning peaker plant off Pulaski Street. The capacity resource known as Project 2015A is a new, efficient, fast-starting, 60 MW, dual fuel, simple cycle peaking electric generating unit and ancillary equipment owned by MMWEC (Massachusetts Municipal Wholesale Electric Company) and located in Peabody, Massachusetts at the location of the PMLP (Peabody Municipal Light Plant) Waters River Station site.

According to applications for permits, Special Project 2015A will emit nearly 51,000 tons of the greenhouse gas carbon dioxide into the atmosphere every year—the equivalent of adding 11,000 combustion engine cars to Massachusetts’ roads each year. Furthermore, the peaker plant will require installing a natural gas compressor to increase natural gas pressure, a 90-foot smokestack and a 2,500-7,500 gallon new tank to hold aqueous urea.”

This view of the plant was revealed recently when parked vehicles were moved at the 58R Pulaski St address.

photos by Sophie Noelle Hartley

]]>
2776
Current status of Peabody’s gas-and-oil peaker plants Series, #1 – SP2015, Peabody’s newest plant and, hopefully, the last new fossil fuel infrastructure to be built. https://breathecleannorthshore.org/2023/10/11/current-status-of-peabodys-gas-and-oil-peaker-plants-series-1-sp2015-peabodys-newest-plant-and-hopefully-the-last-new-fossil-fuel-infrastructure-to-be-built/ Wed, 11 Oct 2023 18:03:59 +0000 https://breathecleannorthshore.org/?p=2761 PMLP announced last month that the new 60MW generator is “physically complete” yet it continues to violate the June 2023 deadline to be ready to provide energy to ISO-NE on request.

“So far, there’s been no penalties for Peabody,” PMLP Manager Joe Anastasia said. He explained that problems moving forward are “administrative” and involve an issue between MMWEC and PMLP regarding ownership of the common hardware being used for the plant.

As proposed, the new plant appears to rely heavily on sharing PMLP resources. In addition to sharing .6 acres of the City’s land off Pulaski Street, the facilities to be shared include:

– provide the new plant with natural gas via the Waters River site’s connection;

– allow the new plant to connect with the regional high voltage transmission system by connecting to a PMLP substation

– share a new, 200,000 gallon oil storage tank with both facilities

Another “arms-length” agreement to share facilities includes maintenance support from PMLP for the new plant. The project will share (and pay PMLP for the use of) some ancillary facilities at the site, such as the oil unloading facility, and MMWEC planned to contract certain “routine maintenance” activities to PMLP.

The new plant was first proposed 8 years ago and was originally to be completed by Summer 2021. That deadline was extended by two years to Summer 2023. That means, ISO-NE expects the new plant is ready to provide electricity to the energy grid. If it calls on the new plant and it does not provide the back-up energy requested, IS0-NE can issue a fine. Is that fine charged to MMWEC? Will they pass that cost on to the 14 communities invested in the plant? Peabody is responsible for 30% of the plant’s cost. Could we see a bill for 30% of any fine that might occur?

The city owns, but PMLP controls and operates the two existing peaker plants at the Waters River station. The new plant is owned by MMWEC.

PMLP’s website announced they will soon re-name the new plant, eliminating SP2015A (Special Project2015A).

Coming Soon: #2 – Status of Generators 1 & 2

Caption:  Wondering if the new smokestack at the plant is complete?  This photo was taken October 10.  Is the smokestack 90 feet high as proposed?  The red box is a 31-foot-tall rectangular stack installed 52 years ago.

]]>
2761
Public Input A Must in Power Plant Projects: State Representatives https://breathecleannorthshore.org/2023/09/01/public-input-a-must-in-power-plant-projects-state-representatives/ https://breathecleannorthshore.org/2023/09/01/public-input-a-must-in-power-plant-projects-state-representatives/#respond Fri, 01 Sep 2023 19:19:01 +0000 https://breathecleannorthshore.org/?p=2729 Go Reps Kerans, Walsh and friends! from Peabody Patch
https://patch.com/massachusetts/peabody/public-input-must-power-plant-projects-state-representatives?utm_source=facebook&utm_medium=web&utm_campaign=share&fbclid=IwAR2p0TVGeMWI5EFsfZnz_YAntXY1ou1IaClY8W7t9QII9j_IscV7wMHvUOQ

]]>
https://breathecleannorthshore.org/2023/09/01/public-input-a-must-in-power-plant-projects-state-representatives/feed/ 0 2729